Monday 14 November 2016

Week Twenty-One: Driveway Poured, Timber-Look Flooring Installed, Kitchen Splashback & Shelving

Another busy week :-)

We had a fair few things happening, but very impressed with the speed.

Driveway was poured at the beginning of the week. Driveway will need to be sealed next week. It's looking great! Our back step has also been poured.

We weren't expecting the flooring to start until the following week, but lo and behold, the laminate was completed by Friday. It looks amazing, we're really happy with it!

Splashback also appeared towards the end of the week, as did the shelving in all the pantries and cupboards.

Only carpet and kitchen waterfall edges to go. Rubbing hands together with glee... Some photos.

Driveway and Back Step




Kitchen Splashback

Shelving





 Timber-Look Flooring: In Progress



 Timber Look Flooring: Complete


 Close up of Bathroom