Thursday, 22 September 2016

Week Fourteen: Waterproofing, Plumbing/Electrical and Timber Cladding

Still moving along at a good pace but a much slower week than usual. The waterproofing in the wet areas was done this week. We also have had plumbers and electricians in and out getting everything ready for the kitchen/bathroom fit outs next week.

Rocked up today not expecting anything and the timber cladding had been applied. I'm really rapt with how it looks. We'd assumed the cladding would be smooth, but it has a grooved 3D effect. I think it looks amazing.

On school holidays now so looking forward to seeing the progress over the next two weeks :-)

Some pictures...






Thursday, 8 September 2016

Week Eleven: Cladding, Eaves and Insulation

Busy week. We had the cladding attached under the eaves. The insulation trades also arrived and were busy little bees. Our lounge room had the sound-proofing applied and more electrical stuff happened. Very exciting!

Some pictures...