Saturday 5 November 2016

Week Twenty: Shower Screens, Mirrors, Air Conditioning, Driveway Prep

And we're still moving along...

We had the shower screens and mirrors installed on Monday of this week. The air conditioning unit was installed as well, including the ceiling vents.

I went past on Friday and the earth movers had been in, digging out the driveway ready to start the following Monday (tomorrow).

We also found out that they have installed the wrong electrical thing-a-me-jig (don't you love my technical jargon?). Something to do with phase power? Anyhow, it should be rectified soon.

We can expect the driveway this week, which I'm really looking forward to. The flooring, kitchen splashback and waterfall bench will be the last things completed. A few days later we will do our walk through. Our site supervisor is expecting that we'll have our keys in three weeks if there aren't any major problems, or four weeks if they've stuffed up!

Happy days!